lumenparty
AI agents for Claude Code: a party of subagents, skills, zero-token guard hooks and a merge gate, for Flutter, mobile and web apps.
- Party
- 16 subagents
- Skills
- 14
- Hooks
- zero-token
- Gate
- merge gate
The pinned cards below are public and MIT licensed. Clone them, open an issue, take what helps. Product work further down is mostly private client code, so those cards link nowhere on purpose.
Packages and tools I build and maintain on my own time. Stars and last push are read live from GitHub.
AI agents for Claude Code: a party of subagents, skills, zero-token guard hooks and a merge gate, for Flutter, mobile and web apps.
Play Install Referrer on Android and Apple AdServices on iOS behind one typed API, for install attribution and deferred deep links. Ships with wherefrom_builder for the server side.
Fails widget tests when a widget rebuilds more than its measured budget. Headless in flutter test: no device, no probes in production code.
Catches App Store and Google Play rejections before review: lints Info.plist, privacy manifests, entitlements and AndroidManifest in CI.
Check that an Android APK or AAB is 16 KB page-aligned before uploading to Play, and name the library that is not. "Could not verify" gets its own exit code, because it is not a pass.
Finds the real audio format (WAV, FLAC, MP3, AIFF, M4A) and exact duration from file bytes, in pure Dart.
Finds widget-test code that hangs in FakeAsync, and fails a stalled testWidgets fast with a reason.
Builds Flutter plugins with or without a closed-source native SDK: SwiftPM, CocoaPods and Gradle wiring that links the vendor binary when present and a stub otherwise.
Indonesian structural design checks in strict SI units: SNI 1729 steel flexure and shear, SNI 2847 concrete, SNI 1727 load combinations, SNI 1726 base shear. Refuses cases it does not implement rather than approximating them.
Irrigation design against the KP criteria: open channel hydraulics, channel design, water requirement through the efficiency chain to the intake, weir and gate discharge. Newtypes keep m³/s, l/s and mm/day apart.
Check an openBIM IFC model against SNI requirements. A rule that cannot read what it needs reports "not evaluated", never a pass, so a clean report cannot hide a model nobody looked at.
Mostly private client code, so only the live products link anywhere.
MVP for a coffee business, web storefront + internal dashboard: system structure, responsive UI, order management flow. Live at koriru.coffee.
Spotify-style music streaming app, playlists, search, and playback UI built in TypeScript.
Multi-feature Flutter app in Clean Architecture, code-gen-free reactive state with Riverpod 3, offline-first via Hive and Dio.
Weather mobile app in Flutter, forecasts and local conditions, built mobile-first.
81 delivered across Central Sulawesi between 2021 and 2025: public buildings, offices, sports facilities, roads, drainage, and landscape works for provincial government agencies. Plus international consultancy work abroad: embankment, drainage & box culvert design in Cova Lima, Timor-Leste (2023).
Roles span the full lifecycle: site supervision and quality control during construction, design and DED review before tender, planning and cost analysis at inception, and HSE oversight throughout. Sorted by completion date. Open any row for scope, responsibilities and outcome.
Scope. Took over construction supervision on a strategic provincial public building project after the previous supervision team left the role vacant.
Outcome. Closed the supervision gap with accountable, reconstructed technical reporting. Design-to-site discrepancies were mitigated before they could affect structural safety.
Buildings
Scope. Planned and supervised workstation power outlet installation, focused on efficient layout and electrical safety.
Outcome. Unit shortfalls were resolved through contractor negotiation. Installation delivered a tidy, safe result compliant with electrical standards.
Interiors and fit-out
Scope. Planned sports field rehabilitation within the official residence complex to upgrade recreational facilities.
Outcome. Rehabilitation planning was completed for the sports field, setting up an upgrade in recreational facilities for complex residents.
Sports and public
Scope. Managed procurement and installation of indoor and outdoor signage for a comprehensive wayfinding system.
Outcome. Cross-unit coordination was completed, delivering a fully functional, integrated wayfinding system.
Interiors and fit-out
Scope. Managed the full interior renovation cycle from planning (DED/HPS) through construction supervision, delivering a functional, representative workspace.
Outcome. User request changes were managed effectively without technical deviation. The workspace was completed functional and representative, meeting the target.
Interiors and fit-out
Scope. Planned and supervised fence/parking area painting and road marking, with a clear layout and complete as-built documentation.
Outcome. Scheduling was synchronized with parallel road works. Circulation and parking became better organized under a clear marking system.
Roads and bridges
Scope. Carried out survey and maintenance planning for the office building to sustain operational function.
Outcome. The maintenance program was structured systematically, prioritized by urgency and operational impact.
Buildings
Scope. Planned procurement and installation of a mezzanine to optimize warehouse storage capacity.
Outcome. The installed mezzanine significantly increased warehouse storage capacity without expanding the building footprint.
Interiors and fit-out
Scope. Designed and supervised installation of decorative lift lobby backdrop panels with strict quality control and HSE compliance.
Outcome. HSE was enforced consistently despite site-level resistance. Visual quality met the design intent, with complete documentation.
Interiors and fit-out
Scope. Continued the 2023 fence planning with budget and design adjustments, and served as the project's HSE expert.
Outcome. Completed the project safely with no recorded incidents. Established a safety culture despite local workforce resistance to HSE protocols.
Roads and bridges
Scope. Led continued 4th-floor interior rehabilitation covering conference, archive, and support rooms, with full control from design through execution.
Outcome. HSE standards were maintained throughout material lifting. Rooms met operational needs with optimal finishing quality.
Interiors and fit-out
Scope. Completed remaining infrastructure improvement works to meet the year-end completion target.
Outcome. The project was completed within the target timeframe, achieving full infrastructure scope with quality maintained.
Roads and bridges
Scope. Developed a digital platform for state building technical-assistance services, integrating standardized cost formulas.
Outcome. The digital platform concept was successfully developed, setting up more efficient, standardized technical assistance service province-wide.
Other
Scope. Continued the infrastructure upgrade program, focusing on drainage cover procurement for pedestrian safety and aesthetics.
Outcome. Installed drainage covers improved pedestrian safety and the visual quality of the walkway within the office complex.
Drainage and water
Scope. Audited the DED document's technical and budget content to eliminate administrative errors and cost items lacking technical justification.
Outcome. Eliminated budget waste risk at the planning stage. The DED was certified fit for use with no major revision needed at the construction stage.
Survey and design
Scope. Engineered the conversion of a former emergency command post into a functional canteen through comprehensive rehabilitation of the roof, interior, and landscape.
Outcome. Managed the variation order strategically to add value. The canteen was made ready for operation with complete, comfortable facilities.
Buildings
Scope. Planned and supervised construction of a canopy and rear fence to complete the office facilities.
Outcome. Completed the canopy and fence, rounding out the office facilities. The rear area is now sheltered and secure.
Buildings
Scope. Conducted a rapid DED review and bill of quantities verification to confirm accuracy, cost efficiency, and compliance with the latest tax regulation (12% VAT).
Outcome. Preserved cost efficiency despite the tax rate increase. The document was made ready for construction with no major revision required.
Survey and design
Scope. Prepared survey, DED, bill of quantities, and technical specifications for the official residence rehabilitation, structured across two phases due to budget constraints.
Outcome. The project was accelerated and completed 100% one week ahead of the deadline, despite entering a critical contract stage (90% of the schedule elapsed).
Buildings
Scope. Prepared a comprehensive plan for the renovation of the High Prosecutor's Office Assistant for Development's official residence.
Outcome. Delivered a complete set of planning documents, ready for use as the basis for construction.
Buildings
Scope. Managed planning and supervision of ACP installation on the main facade columns, mitigating material delay risk.
Outcome. Achieved 84.17% of the contract target within the contract deadline. The remaining works were completed in early January without compromising quality.
Interiors and fit-out
Scope. Led a comprehensive infrastructure improvement project covering building and road repairs across the office complex.
Outcome. Infrastructure improvements were completed comprehensively. The office complex saw a significant upgrade in function and appearance.
Roads and bridges
Scope. Continued Phase II landscape works, focusing on the garden area and supporting facilities.
Outcome. Maintained design continuity, with Phase I and Phase II fully integrated.
Sports and public
Scope. Planned and executed billboard structure rehabilitation against an accelerated completion target.
Outcome. Met the 2-week accelerated target. Work finished ahead of the contract schedule.
Interiors and fit-out
Scope. Carried out a condition assessment of the madrasah library building to support planning for educational facility upgrades.
Outcome. The assessment was completed with clear technical recommendations, giving the school a roadmap for library facility upgrades.
Survey and design
Scope. Conducted inspection and valuation of the BPBD building's condition to determine rehabilitation or replacement needs.
Outcome. Delivered a comprehensive inspection and valuation report, giving management a technical data basis for budget planning.
Survey and design
Scope. Designed and supervised building demolition in accordance with Permen PUPR No.18/2021, with a focus on safety and construction waste management.
Outcome. The post-earthquake structure was demolished safely with zero accidents. Full documentation was maintained for accountability.
Buildings
Scope. Conducted a physical condition survey of cultural heritage sites to support preservation efforts and heritage documentation.
Outcome. Delivered comprehensive site condition documentation, providing the data basis for the region's cultural heritage preservation program.
Survey and design
Scope. Engaged as technical expert to review a rehabilitation package uploaded via e-catalog, identifying critical errors in the consultant's cost estimate.
Outcome. The original documentation would have deterred contractors from bidding due to unrealistic pricing. The cost correction ensured the project could proceed on a transparent, realistic basis.
Buildings
Scope. Designed the landscape for the rear segment of the BPKAD building, integrating functional and aesthetic elements.
Outcome. Delivered the landscape to the technical plan, ready for the office's outdoor activities.
Sports and public
Scope. Responsible for planning, DED, and cost estimation for new warehouse construction, incorporating reused post-disaster materials.
Outcome. Progress ran 41% ahead of the July 2024 schedule. Structural adjustments were managed without compromising safety.
Buildings
Scope. Continued 2023 landscaping works with a focus on the rear garden area, including cost estimation and technical supervision.
Outcome. Finished ahead of schedule despite coordination challenges from working at night to accommodate daytime parking use.
Sports and public
Scope. Conducted land survey and measurement for planning a clinic facility at the Central Sulawesi High Prosecutor's Office (Kejaksaan Tinggi).
Outcome. Survey results became the official reference for project preparation, ensuring accurate land allocation per regulatory requirements.
Survey and design
Scope. Assigned to carry out a measurement survey (opname) for a stalled road project at Opportunity Stage, uncovering 20.24% of works incomplete.
Outcome. Identified the project delay as stemming from contractor-internal issues. Measurement was completed in a single day despite extreme, hazardous conditions.
Roads and bridges
Scope. Planned and supervised interior procurement, including the Head of Department's rest room and a lobby backdrop featuring the CIKASDA logo.
Outcome. The CIKASDA logo introduced remains in use today as the institution's identity. The rest room was successfully concealed to meet requirements.
Interiors and fit-out
Scope. Reviewed Phase I works and prepared the Phase II interior continuation for inter-division rooms and meeting rooms.
Outcome. Completed the project efficiently within the contract period. Non-technical issues (worker apprehension, adhesive odor) were managed through guidance and schedule adjustment.
Interiors and fit-out
Scope. International design consultancy: designed a comprehensive flood control and drainage system for an infrastructure project in Cova Lima, Timor-Leste, marking a first international project assignment.
Outcome. Overcame limited field data through engineering judgment. Completed a first international project, broadening technical perspective across borders.
Drainage and water
Scope. Planned and supervised rehabilitation of an indoor sports facility, a former tennis court converted to futsal use.
Outcome. Adaptive reuse extended the infrastructure's service life. Safety and sanitation upgrades improved staff recreational use.
Sports and public
Scope. Planned and supervised continued partition works across all division rooms, including detailed finishing.
Outcome. Completed the project one week ahead of schedule with no variation order. Night-shift work ensured uninterrupted office operations.
Interiors and fit-out
Scope. Planned and supervised landscape works integrating functional elements with megalithic cultural ornamentation.
Outcome. The megalithic ornamentation fell short of the design vision due to the contractor's limited grasp of cultural context; other landscape elements were completed successfully.
Sports and public
Scope. Planned and supervised drainage and water management infrastructure works at the office complex.
Outcome. An owner-directed change (catch basin converted to storage tank) compromised infiltration function; the recommended correction was declined on budget grounds.
Buildings
Scope. Planned and supervised procurement of workstation partitions and camouflage elements for the BPKAD interior.
Outcome. Managed the complexity of multiple parallel packages through tight timeline coordination. Discrepancies between the DED and actual site conditions were resolved through scope adjustment.
Interiors and fit-out
Scope. Planned and supervised procurement of windows and doors for the BPKAD office interior decoration works.
Outcome. Managed dependency on the BPKAD Phase II architectural package through timeline coordination, completing the project efficiently once the architectural phase concluded.
Interiors and fit-out
Scope. Supervised construction of a stationery warehouse for BPKAD, addressing documentation that had bypassed review.
Outcome. Resolved multiple variation orders and addenda required due to double-counted volumes in the consultant's documents; contractor integrity ensured transparent correction.
Buildings
Scope. Reviewed planning documents and supervised Phase II construction of the BPKAD building, with a focus on architectural and MEP works.
Outcome. Resolved financial reconciliation through a detailed inspection process, reaching completion despite multi-contractor coordination challenges.
Buildings
Scope. Reviewed the consultant's documents and supervised architectural, supporting-building, and landscape works for the continuation of the Rumah Gadang.
Outcome. Coordination with a professional contractor kept progress running smoothly. Owner-driven design changes were managed through an addendum without disrupting the main schedule.
Buildings
Scope. Prepared design and technical documentation for an orphanage facility as a pro bono contribution to improving welfare for orphaned children.
Outcome. Delivered a functional design meeting the social institution's needs, a pro bono contribution reflecting the engineer's civic responsibility.
Survey and design
Scope. Planned and supervised comprehensive maintenance covering architectural, electrical, sanitation, and mechanical works.
Outcome. Addressed extensive damage within a limited budget, with progress ahead of schedule despite complex septic repair challenges.
Buildings
Scope. Planned and supervised construction of toilet facilities and supporting utilities for a campground at a remote site.
Outcome. Completed the project using local labor. Remote-site access and budget constraints were managed through a 'just-fit' design approach.
Sports and public
Scope. Prepared planning documents for a comprehensive upgrade of Toli-Toli Port facilities.
Outcome. Completed the planning without a direct site survey, relying on photos, sketches, and secondary documentation, a resourceful approach that overcame data limitations.
Roads and bridges
Scope. Planned and supervised fence rehabilitation, including asset write-off, demolition, and new construction with signage.
Outcome. Site verification uncovered discrepancies in the contractor's claims. Technical integrity was upheld through direct inspection despite administrative pressure.
Buildings
Scope. Prepared DED and cost estimates for a donated canopy sheltering the kindergarten's play yard.
Outcome. Delivered a practical design fitting the donor's funding model, with a natural-landscape alternative recommended for longer-term benefit.
Survey and design
Scope. Designed and formulated the Standard Cost Budget for the entire Central Sulawesi Province in response to a request from BPKAD and the KPK.
Outcome. Completed the project independently despite its complexity repeatedly freezing laptop and PC hardware. The resulting formula became a national reference used across provinces in Indonesia.
Survey and design
Scope. Designed washroom and ablution facilities for an Islamic boarding school as a social contribution toward improved student infrastructure.
Outcome. Delivered the design overnight, ready for implementation, as a pro-bono professional contribution to the religious education institution.
Drainage and water
Scope. Planned and supervised rehabilitation of the front fence and office frontage, integrating Kaili cultural ornamentation.
Outcome. Reached 60%+ progress at contract midpoint and 100% within three weeks. Upgraded the office's visual identity with local cultural elements.
Sports and public
Scope. Planned and supervised construction of an office name wall to modernize the facade with ACP cladding and acrylic signage.
Outcome. Completed the project in under one week, well ahead of schedule, with HSE maintained throughout work at height.
Interiors and fit-out
Scope. Planned and supervised upgrades to the badminton hall to improve playing quality and comfort.
Outcome. Completed the project ahead of schedule with no variation order, significantly upgrading the facility's comfort and playing standard.
Sports and public
Scope. Carried out an independent survey and prepared a fence design for a corner lot at a strategic intersection.
Outcome. Completed the design within one week. The site, now a building materials store, reflects the early planning contribution to the land's development.
Survey and design
Scope. Planned and supervised landscape works and drainage repair at the Kajati official residence.
Outcome. Resolved habitability issues through an integrated drainage, canopy, and landscape solution.
Sports and public
Scope. Planned and supervised rehabilitation of severely damaged sanitation facilities and supporting infrastructure at the stadium.
Outcome. Completed rehabilitation despite execution coinciding with Ramadan. The new water system operates with high-capacity pumps to overcome site elevation.
Sports and public
Scope. Prepared a design concept and cost estimate for a modest resort facility.
Outcome. Delivered a functional design and cost estimate matched to the client's needs through an efficient approach.
Survey and design
Scope. Planned and supervised aviary landscaping works at the Vice Governor's official residence complex.
Outcome. Completed the project one week ahead of schedule with no variation order. Large-material logistics challenges were resolved through creative access planning.
Sports and public
Scope. Planned maintenance of the warehouse and sports facilities to preserve operational and recreational function.
Outcome. Maintained the facilities in good condition, with the warehouse fully operational and sports facilities ready for staff use.
Sports and public
Scope. Reviewed and supervised restoration of the Souraja (traditional Kaili house) as a post-disaster cultural heritage preservation effort.
Outcome. Souraja was restored with its cultural and historical value preserved. The building now serves as a center for Kaili traditional activities.
Buildings
Scope. Planned side fence construction to complete the security system and perimeter aesthetics of the official residence.
Outcome. The fence was completed with seamless integration into the landscape. The official residence's security perimeter now holds consistent aesthetics.
Buildings
Scope. Reviewed the DED and supervised construction of the Rumah Gadang as a symbol of Minangkabau cultural heritage in Palu City.
Outcome. Rumah Gadang Phase I was completed with architectural authenticity preserved. The project stands as a Minangkabau cultural landmark in Central Sulawesi.
Buildings
Scope. Planned partition supply to divide divisional workspace into more functional areas.
Outcome. The workspace was organized with functional partitioning. Staff privacy and focus improved without compromising collaboration.
Interiors and fit-out
Scope. Planned rehabilitation of the 4th-floor meeting room to increase capacity and comfort for meeting activities.
Outcome. The meeting room was upgraded with modern facilities. Capacity and comfort improved to support coordination activities.
Buildings
Scope. Planned a maintenance program for the Bidarawasia building to extend service life and preserve operational function.
Outcome. A systematic maintenance program was delivered. The building's condition is maintained through timely intervention on critical components.
Buildings
Scope. Planned a comprehensive landscape design for the Deputy Governor's official residence to a representative standard.
Outcome. The landscape was completed to a high representative standard. The official residence now has grounds reflecting beauty and stature.
Sports and public
Scope. Planned interior renovation of the guest pavilion to VIP standard for receiving important guests.
Outcome. The pavilion was upgraded with a premium interior. The facility is now fit to receive VIP guests to a high protocol standard.
Interiors and fit-out
Scope. Prepared a comprehensive DED for office interior renovation, focused on functionality and professional aesthetics.
Outcome. A comprehensive interior DED was delivered. The design accommodates every division's needs to a high professional standard.
Interiors and fit-out
Scope. Planned rehabilitation of a green open space to improve environmental quality and public space in Tavanuka Sub-District.
Outcome. The green open space was delivered as a quality public space. Residents gained a green recreational facility that improves quality of life.
Sports and public
Scope. Planned supply and installation of glass partitions to modernize the official residence's interior.
Outcome. Glass partitions were installed to a high safety standard. The official residence's interior is now more modern and light-filled.
Interiors and fit-out
Scope. Planned and supervised construction of decorative landscape elements, including a gazebo, fish pond, and aviary, to complete the residence complex.
Outcome. The premium landscape facilities were delivered as planned. Close supervision ensured optimal construction quality.
Drainage and water
Scope. Planned and supervised garden works and podium construction at the office frontage to improve the public area's aesthetics and function.
Outcome. The garden and office podium were delivered as planned. The office frontage is now more representative and functional.
Sports and public
Scope. Planned supply and installation of decorative grilles to enhance the office building's facade aesthetics.
Outcome. Decorative grilles were installed, strengthening the building's visual identity. The office facade is now more distinctive and representative.
Interiors and fit-out
Scope. Planned rehabilitation of the Provincial PKK building, focused on improving building function and aesthetics.
Outcome. A complete rehabilitation planning package was delivered. The PKK building's function was upgraded to meet organizational needs.
Buildings
Scope. Planned and supervised partition installation to optimize the workspace layout on the office building's 4th floor.
Outcome. The workspace was upgraded with modern partitioning. Staff productivity improved through a better-organized layout.
Interiors and fit-out
Scope. Prepared working drawings and cost estimates for a Type 36 BTN standard residential house.
Outcome. Planning documentation was delivered to BTN standard. The efficient design maximized space within Type 36 constraints.
Survey and design
Scope. Designed a riverside residence with an integrated fish pond facility to support family income.
Outcome. The design was completed integrating residential and fish farming functions. A creative solution made use of the riverside site's potential.
Drainage and water
Scope. Conducted a topographic survey of the salt pond area following the tsunami to support infrastructure reconstruction and recovery.
Outcome. The post-disaster survey documented significant land morphology change. The data became the basis for restoring salt production infrastructure.
Drainage and water